Moving Right Along

Progress in the last week: siding installation is underway; the well was drilled with success; the garage doors were installed; copper lines for the ductless mini-split system were run; the plumbing and electrical rough-ins were finished. Today we had the rough inspection. A few minor things need to be done and we’ll have the inspector come back on Thursday to take another look. Looks like insulation will be installed starting Friday, and if we stay on pace, we could be starting drywall next week! We are currently on track to finish in early November.