Updated Details

Here are a few pictures of recent progress. We are in a bit of a slowdown while we wait for the concrete polisher, who will start in early August. After that, the windows can be installed, and then we will have a weather-tight house. We met with the electrician for two hours on Friday to begin laying out the fixtures and outlets and we only got through the upstairs. We will lay out the downstairs after the concrete is finished and the interior walls can be completed. The plumber will start the rough plumbing for the upstairs shower and tub this week. And as of Friday, Eleanor is enrolled in the Bolton Center School!

Advertisements

Taking Shape

View across the field to the south elevation.

View across the field to the south elevation.

With the addition of the roof trusses during last week’s heat wave, the full volume of the house is now apparent. Our team of carpenters is turning their attention to air sealing details and window installation.